The short version

Vancouver-based Lithium Americas increased its estimated Phase 1 capital cost for the Thacker Pass lithium project in Nevada to US$3.83 billion on November 11.

Construction budget climbs substantially

Lithium Americas says its definitive estimate for the first phase of its Thacker Pass project has risen from US$2.93 billion to US$3.83 billion, an increase of about 31%. The company attributed the rise to labour, installation, engineering and logistics costs, including effects of tariffs and freight conditions. Reuters reported the shares fell in Wednesday morning trading as investors assessed the higher capital requirement.

Production target remains in place for now

The company says mechanical completion is still planned for late 2027, followed by a ramp-up toward commercial output in 2028. Full production capacity is projected at about 40,000 tonnes of battery-quality lithium carbonate annually. These are company targets, not completed production milestones. A higher cost estimate can affect investment returns even when the target construction schedule remains unchanged.

Capital and battery supply-chain implications

Lithium is a key raw material in many electric-vehicle batteries. Thacker Pass is a joint venture involving General Motors and has backing through U.S. energy financing arrangements. The company says it expects to fund the incremental requirements with available financing sources and contributions, but further costs, commodity prices or delays could change the outlook. CDN News will report independently verified commissioning and output when available.

Follow the evidence

Sources & transparency

Lithium Americas — Thacker Pass update, November 11Reuters — Lithium Americas raises cost by 31%, November 11

Original CDN News coverage. Sources are linked for reference.

Source linked ·

Request a correction